Overall Project Status
The extension from Abbott Street to Hazeldean Road is actively under construction, with completion projected for Fall 2025
The project is part of the City of Ottawa’s capital infrastructure plan and responds to growing development in Stittsville and Kanata
🔸 Phase II – Abbott Street to Hazeldean Road
Hazeldean Road Intersection
Median and civil construction are ongoing and approaching finalization.
Intersection is scheduled to be fully reconfigured, with signal infrastructure installed early December 2025.
Final resurfacing and minor bituminous works to resume in 2025 .
Abbott Street Roundabout
Cleanup operations planned before winter: excavation backfill, fence removal, and paving touches where settling has occurred.
Remaining roundabout improvements delayed until summer 2025 .
Corridor Infrastructure (Hazeldean ↔ Abbott – Future Abbott’s Run Subdivision)
Installation of underground sanitary, storm, water, and electrical services is largely complete.
Paving for the northern section of Robert Grant Avenue (towards Hazeldean) slated to begin within the coming week
🔸 Engineering & Investment Details
The project is valued at approximately $35 million, executed under a front-ending agreement between the Fernbank Land-Owners Group and the City
Phase II—covering the Abbott ↔ Hazeldean stretch—is currently in full swing